Capital Projects

Westwood Park

Westwood Park Construction Update – 6/23/2026
The boardwalk connecting Westwood Park & the Community Center properties is 90% complete. The t-ball fencing install is progressing as well and almost complete. The shade structure near the pickleball courts has been installed. The footprint for the band shelter has been finalized. The front apron, stairs, and band shelter floor have been poured.

Westwood Park Construction Update – 6/2/2026
Construction work is progressing nicely at Westwood Park. All of the new paths have been laid out with base material installed. The Pickleball and Band Shelter locations have also been laid out, with earthwork and base material installation ongoing. Curbs for both the parking lot and pickleball courts have been poured. Crews are currently working on installing the fencing for the t-ball field, and forming and pouring the stairs on the band shelter.

Westwood Park Construction – Week of May 4th Update:
Construction officially started on Monday April 27th. A fair amount of preliminary earthwork has been performed. The majority of the new paths have been laid out with base material installed. The Pickleball and Band Shelter locations have also been laid out, with earthwork and base material installation being performed.